Client
Ashfield Developments
Value
£ 3,700,000
Size
22,873 sq ft
Location
Worcester
Duration
38 Weeks
Project
Overview

The project at JVM Castings in Worcester was completed in two phases. Phase 1 involved site re-organisation, by creating a new staff car park with electric vehicle charging points by demolishing a number of out buildings, a covered cycle store, and a dedicated heavy goods vehicle access for JVM Castings on a largely under-utilised part of the site.

The construction of a new Lidl foodstore was undertaken during Phase 2 and included extensive Section 278 works to allow access to the plot. The Section 278 works included the development of two new entrances, resurfacing of the highway, relocating utilities running the length of the project and bus shelter positioned out sight of the site.