Benniman completes construction of £15 million Northants warehouse

RN9A9866

A £15 million warehouse unit has been unveiled at a flagship development in Northamptonshire.

Benniman constructed the 183,280 sq ft unit for leading logistics developer and manager, St. Modwen at St. Modwen Park Wellingborough.

Located at Stanton Cross, on the eastern edge of Wellingborough, U184 completes phase 2 of the development.

The project comprised 40,000m³ earthworks remodelling and the installation of 180 linear metres of retaining wall and took 40 weeks to complete. It was designed by UMC Architects

Tim Mills, Procurement Director, at Benniman, said: “We’re pleased to have completed work on this latest modern, detached warehouse for St. Modwen in this prestigious development. It is rewarding to have delivered another high-quality unit achieving BREEAM Excellent and an EPC A+ Rating for our client.”